Burlington canal lift bridge to undergo maintenance work in July during the evenings.

News 100 redBy Staff

July 7, 2017

BURLINGTON, ON

 

The Burlington Canal Lift Bridge will be closed for periods of time between July 10 and July 29, 2017.

The bridge will be closed overnight to vehicular and pedestrian traffic in both directions between 8 pm and 5 am during the following periods:

from Monday, July 10, to the morning of Saturday, July 15
from Monday, July 17, to the morning of Saturday, July 22
from Monday, July 24, to the morning of Saturday, July 29

Burlington_Canal_Lift_BridgeRush hour and marine traffic will not be affected.

This schedule may change because of weather conditions or logistical requirements. PSPC will publish notices regarding any schedule changes.

The closures are required as part of the project to replace the bridge’s controls, drives and cables.

The replacement of key components of the bridge’s lift system will extend its serviceable life, meeting the needs of both marine and vehicular traffic in the area.