It’s a done deal. Council to approve pier contractor Sept 26th. Council members may dance on their desks.

By Pepper Parr

BURLINGTON, ON September 14, 2011 It’s done. The city’s Community Services Committee approved an Engineering department recommendation to go with the bid submitted by Graham Infrastructure to complete the construction of the Brant Street Pier at a cost to the city of $6,429,700.

Every member of council voted FOR the recommendation – all in favour votes by this Council have not been the norm. The matter goes to a regular Council meeting on September 26th where it becomes legal. You can expect to see construction people on the site the next day.

The Council committee went for the whole package which added $283,360 to the price which included the extension of the promenade from the edge of the pier right up to Lakeshore Road and for the access ramp that will let people get to the small mini beach that has formed on the west side of the pier.

They deferred on a floating dock on the west side of the pier even though councilor Dennison pushed a bit to get that included. What happens next?

Here’s the schedule:

Finalize contract and mobilize the construction team – October 2011

Site preparation/Steel removal – November/December 2011

Much of the steel used in the first phase was found to be deficient and will have to be removed.

Steel fabrication – November 2011 – March 2012

New steel beams that meet the design specifications has to be fabricated and delivered to the web site.

Steel installation – April May 2012

This is the point where it all begins to come together.

Deck and beacon construction May to December 2012

The beacon, which we’ve heard very little about gets built during the phase of construction.

Winter shutdown    December 2012 to March 2013

An early winter or a long winter could extend this phase. If it is a mild winter some time may be gained.

Total completion, grand opening – April – June 2013

 

Council looks for re-lection November 2014

The first major task is the removal of tons of steel beams that are deficient.  Some of the beams that were never used are shown above.  Who will get the funds recovered from the sale of this scrap steel?

The first major task is the removal of tons of steel beams that are deficient. Some of the beams that were never used are shown above. Who will get the funds recovered from the sale of this scrap steel?

There was a very satisfied feeling in the Council chamber when all seven hands went up approving the recommendation. And they have every reason to be satisfied – they worked long and hard and overcame several significant obstacles.

There are legal points to be argued with the claims the city is making against the original contractor and the designer – but those are matters for another day. Wednesday, September 14th was a win day for this council and they deserved to feel pleased with what they had achieved. The Engineering people deserved the credit they were given

The total project cost, including the nearly $5.98 million spent to date, will amount to a total of $14.44 million, which does not include the legal costs.

There is more to say about where we are with the pier project; how we got here and just what those “lessons learned” were. Agreeing to a $6 million dollar project and ending up with a price of $14. million calls for a hard look at what the crowd at the city hall really did. Credit where credit is due, yes – but accountability and laying the responsibility for the mistakes where they belong is also a part of the process. We will cover that story when city council passes the by-law that lets properly qualified contractors begin their work.

Much of the steel from the circle area on the left out to the end of the pier has to be removed and replaced.  The caissons that dig deep into the lake bed are sound and that portion of the electrical system installed is in good shape.  However, three of the light standards seem to have just disappeared.  The Engineering department managed to return the light standards that were unacceptable and has bought twelve new light standards

Much of the steel from the circle area on the left out to the end of the pier has to be removed and replaced. The caissons that dig deep into the lake bed are sound and that portion of the electrical system installed is in good shape. However, three of the light standards seem to have just disappeared. The Engineering department managed to return the light standards that were unacceptable and has bought twelve new light standards

The city has a strong legal case and will probably settle with the designer and the contractor at some point in the legal process but, as the Mayor said during the meeting – “that is something we will handle on another day.

Graham Group of Companies is a North American-wide company, with a local base in Mississauga. Graham is the fifth largest construction company in Canada with more than 1,200 salaried staff and a 2010 revenue of $1.8 billion.

 