That Pier – progress, good solid progress – but we’ve not settled with the bonding company yet.

By Pepper Parr

BURLINGTON, ON May 12, 2011 – There was another update on progress with the building of THE Pier at the foot of Brant Street. This time both the City Solicitor, Nancy Shea Nicol and the Director of Engineering, Tom Eichenbaum were on hand to answer questions. That expensive lawyer from the Big Smoke to the east of us was also on hand to advise and direct. This time he was carrying his smaller briefcase – think that was a good sign.

It looks a little rough today while it undergoes inspections and the drawings to complete the work are brought up to date – but the Pier is coming along just fine.  The city has control of this file now.

It looks a little rough today while it undergoes inspections and the drawings to complete the work are brought up to date – but the Pier is coming along just fine. The city has control of this file now.

Council, as they usually do on this file, went into closed session to talk behind closed doors about the latest from Zurich Insurance on where things stand with the submission they delivered to the city a number of weeks ago. The city is suing the insurance company for several million – asking them to pay up on the performance bond put up by Harm Schilthuis and Sons Ltd. to ensure that they would finish the job. Harm Schilthuis and Sons Ltd., the original contractor walked off the job last December and the city sued both the contractor, the company that designed the Pier and was overseeing the construction and the insurance company that provided the bond.

The City was handling the file rather poorly under the former Council but when the new team took to the horseshoe table in the Council Chambers a new attitude was evident. As well, a number of engineering types are no longer on the city payroll.

The legal stuff will take time but my sense is that the City will prevail and that there will be a settlement in the City’s favour when all is said and done. There is now a Project Management Team (PMT) in place which consists of a professional project management firm (Mettko) and a procurement consultant (Cassels Brock) – we’re not going to be buying any sub standard steel this time around. Recall that there was failure with some of the steel used for the deck of the Pier that failed when there was a concrete pour.

The city is on schedule to have half of the construction drawings ready by June 1. An inspection of the caissons and other parts that are under water has been done – the preliminary report says no problems at that level. The electrical room has been inspected and it is fine. The city is working with the supplier of the light fixtures to determine how to incorporate what has apparently already been purchased into the design.

The site was basically abandoned by the previous contractor, Harm Schilthuis and Sons Ltd. Last December. Working through various contractors, the city has had to go in and ensure that everything is as it should be.

With the drawings that will be available early in June Mettko will prepare an initial cost estimate and then go out to tender in July. Tenders will close in August and a decision made in September as to who the contractor that will build the Pier is going to be.

The Mayor might want to put the Burlington Teen Tour Band on notice that they will be needed Labour Day to March down Brant Street to celebrate the signing of a contract and as a dry run for the Official opening that is penciled in for sometime in June of 2013.

The submission from Zurich Insurance didn’t help when it arrived a number of weeks ago but if the smile on Tom Eichenbaum’s face when he left the closed session of Council Committee last night is any indication – things are going just fine.

The Pier is going to get built and it will open before the summer of 2013.