By Staff
July 19th, 2023
BURLINGTON, ON
The work that has to be done on the Skyway Bridge is disrupting.
Here is the latest update.
On Saturday, July 22, one lane will be closed starting at 8:30 p.m., with full closure at 10 p.m.
The lanes will remain closed until Sunday, July 23 at 11:30 a.m.
Here is the full schedule:
Saturday, July 22
8:30 p.m. – one lane closed
10 p.m. – full closure
Sunday, July 23, 11:30 a.m. – all lanes reopen
Friday, July 28*
8:30 p.m. – one lane closed
10 p.m. – full closure
Saturday, July 29, 10 a.m. – all lanes reopen
*rain date – Saturday, July 29
Friday, Aug. 11*
8:30 p.m. – one lane closed
10 p.m. – full closure
Saturday, Aug. 12, 10 a.m. – all lanes reopen
*rain date – Saturday, Aug. 12
Friday, Aug. 18*
8:30 p.m. – one lane closed
10 p.m. – full closure
Saturday, Aug. 19, 10 a.m. – all lanes reopen
*rain date – Saturday, Aug. 19
On ramps closed
At these times, the QEW Niagara bound on ramps at:
• Northshore Boulevard,
• Plains Road and
• Fairview Street
will be closed.