Skyway Bridge closures are longer than first reported - schedule is for most weekends through to mid August

By Staff

July 19th, 2023

BURLINGTON, ON

 

The work that has to be done on the Skyway Bridge is disrupting.

Here is the latest update.

Closed to Skyway traffic most weekends through to at least mid-August

On Saturday, July 22, one lane will be closed starting at 8:30 p.m., with full closure at 10 p.m.

The lanes will remain closed until Sunday, July 23 at 11:30 a.m.

Here is the full schedule:

Saturday, July 22
8:30 p.m. – one lane closed
10 p.m. – full closure
Sunday, July 23, 11:30 a.m. – all lanes reopen

Friday, July 28*
8:30 p.m. – one lane closed
10 p.m. – full closure

Saturday, July 29, 10 a.m. – all lanes reopen
*rain date – Saturday, July 29

Friday, Aug. 11*
8:30 p.m. – one lane closed
10 p.m. – full closure

Saturday, Aug. 12, 10 a.m. – all lanes reopen
*rain date – Saturday, Aug. 12

Friday, Aug. 18*
8:30 p.m. – one lane closed
10 p.m. – full closure

Saturday, Aug. 19, 10 a.m. – all lanes reopen
*rain date – Saturday, Aug. 19

On ramps closed
At these times, the QEW Niagara bound on ramps at:

• Northshore Boulevard,
• Plains Road and
• Fairview Street

will be closed.