BURLINGTON, ON. February 19, 2013 In the cold winter weather we don’t get out as often which means we don’t get to the waterfront and we don’t get to see the work that is getting done to have THE pier ready for an official opening during the Sound of Music Festival which is about four months away.
The only impediment now is weather. And that so far has been a really doozy up and down situation. In October the schedule lost eleven day: “eleven days in October” exclaimed Craig Steven’s, the city’s man on the project.
November was good as was December with basically nothing lost but January was not as good –there were five days lost and so far in February they have lost four days. “In January: said Stevens, ”we had temperatures that ranged from + 16 to -27. It’s all but impossible to plan – but plan they do and they go forward as well.
The first part of the node is in place. They are now putting the re bar in and getting ready to pour concrete around the base of a structure that will rise four metres and have a beacon atop it that will rise 12 metres for a total height of 16 metres. It will be quite something to see when it is completed.
The beacon part of the node is being fabricated now at a shop in Kitchener where it will go through a final quality control check and be shipped to Burlington and put in place.
The node will have stairs that wind around the side leading to the observation deck.
The feature that will make that pier safe for everyone is the balustrades that will be quite high and be made of galvanized steel which will give them a silver-grey look and aluminum rail and rubbing streak that will be painted with a powder that will be adhered to the surface and done in what construction people in this city like to call Burlington blue.
They will have cable strung through several levels preventing anyone from falling over the side. There will be more than 200 of these stanchions placed around the pier. Falling over just won’t be possible – jumping over – well that’s another matter. Bets are being placed on which high school gets to make that claim to fame first.
The balustrades – what most people call the railings have gone through several modifications which raised the question: why design decisions at this point; which brought the response: “We’ve never gotten this far before”, said Stevens, and indeed after more than six years of work and close to $20 million tax dollars spent – this is as far as construction of the pier has ever gotten.
The node that is now being put together will have a large beacon placed on top of it. That beacon was to be part of the support for the win turbine that got trashed by city council when no one appeared to be able to figure out where the power to light up the pier at night was going to come from or how it would be paid for. A major opportunity to save serious dollars over the life of the pier and to make an important environmental statement was lost.
At the base of the pier, in close to the shore, the mini-beach grows a little more each month. While the lake water level is low right now, once the construction trestle is taken out there might be accumulation of more sand. The city might actually get a boat dock without having to spend a ton of money.
Meanwhile on the legal front the Examination for Discovery process continues. Henry Schilthuis and Sons Ltd., the contractor who is suing the city, and who is in return being sued by the city, has been examined and the Director of engineering for Burlington has gone through part of his Examination. Those proceedings have been adjourned until the week of the 25th of February.
If the temperature out on the pier is cold – the temperature in the Examination for Discovery room is not quite frozen but certainly very frosty. Some painful discoveries are being made.