By Staff
October 22, 2020
BURLINGTON, ON
With the application from Nelson Aggregates complete and accepted, the process of going through the numerous documents presented to support the request for additional licenses can begin.
The process is going to be daunting.
An extension of the Burlington Nelson Quarry would require Provincial, Regional and City approval. There is a sequencing of decisions required and parallel review processes happening at the provincial, regional and city level.
It will be years before there is a decision.
The City of Burlington received an application to amend the Burlington Official Plan designation of the subject lands to expand the existing Nelson quarry operation on May 14th.
Ward 3 Councillor Rory Nisan said “Council is committed to a transparent process and I look forward to the project coming before the council table. I urge Burlington residents to get involved and to ensure their opinions about this application are heard.”
An extension of the Burlington Nelson Quarry would require:
Public consultation and engagement, including a statutory public meeting
Amendments to the Niagara Escarpment Plan and issuance of a Development Permit
Amendments to the Region of Halton Official Plan
Amendments to the City of Burlington Official Plan
An Aggregate License from the Province of Ontario, Ministry of Natural Resources and Forestry for the proposed expansion area
An application to the Niagara Escarpment Commission, Region of Halton and Ministry of Natural Resources and Forestry were received at the same time the City received an application.
A conceptual flowchart showing the parallel review process for the application is set out below. This process includes statutory timelines, application benchmarks, decision points and highlights opportunities for public consultation and engagement.
An inter-agency Joint Agency Review Team (JART) framework will be used to review the application for the proposed quarry expansion to ensure coordinated review by all agencies. The JART consists of technical staff from the Niagara Escarpment Commission, Region of Halton, Conservation Halton and the City of Burlington. The function of JART is to review the completeness of the application and analyze the proposal on its technical merits. JART itself does not make a recommendation on whether or not the application should be approved.
There will be regular reporting to Burlington City Council with progress updates and clarity on timing as the review process unfolds.
Prior to any decisions being made, public consultation will occur, including a statutory public meeting. The timing of the statutory public meeting has not yet been determined and will be scheduled once the technical review of the proposal has progressed further. Residents are encouraged to subscribe to the City’s Nelson Quarry Extension webpage Burlington.ca/nelsonquarry for up to date information on the application.
Communications will go out to residents informing them about the opportunities to engage and provide their feedback on any requests for comments
Both the NEC and the MNRF will be releasing requests for comment on the Environmental Registry of Ontario. This is anticipated to occur within 2020, and the ability for the public, the City and other agencies to comment will be open for a limited time.
Mayor Meed Ward has said: “I know residents across our city and region are watching this very carefully because it affects us all. Our primary consideration will be how this will affect the health and safety of our community and the environment of this very sensitive area. I want to credit our Ward 3 Councillor Rory Nisan in ensuring residents know what is happening and are informed about the process so that they can be involved. There is a long road ahead.”
Related news story: