Parts of King Road closed for 8 weeks while last phase of grade separation is done; fish are using the aqueduct built for them.

September 30th, 2013

By Pepper Parr

BURLINGTON, ON   Santa Claus just might be able to get to some of the homes in Aldershot if he wants to use the King Road grade separation.  The tunnel underneath the railway tracks was pushed through last thanksgiving – a task that was seen as a major engineering feat when it was done.  Getting a creek re-routed and set up so that it would run over the underpass – as an aqueduct – is now operational.  All that’s left to get done is for the road underneath the railway tracks to be built and King Road re-aligned.  THAT is going to take eight weeks.  

That road, King Road, to the right of the tunnel will soon be gone forever and you will actually be able to drive beneath those railway tracks.

The grade separation project is in what city hall calls the final phase that will see total completion anticipated for June 2014

What the city calls the FINAL road closure starts October 15th at 10am, lasting for 8 weeks, to facilitate the move of the road through the underpass. The October road closure will have pedestrian access maintained. At the completion of the road closure you will be able to drive under the railway tracks.  Expect to see every politician in the Region and perhaps even the Premier, who seems to like Burlington, either peddling bicycles under the railway tracks in a flotilla of convertible cars driving through the newly paved road.  And I suppose the Burlington Teen Tour Band will be out with the flags flying.

The project seems to be talking forever – heck they shut down the rail line LAST Thanksgiving and dug the tunnel under the railway line in three days – so someone knew what a day’s work was.

It was a mammoth project, seen as a major engineering feat by many and the core work got done over a three day weekend almost a year ago. Progress has been slow since then – expected to open before Christmas.

The reconstruction of King Road from Plains Road to south of Highway 403 has also been completed, with the exception of the road at the tracks, which will be relocated to the underpass during the October road closure.

The opening up of the King Road underpass has the potential to draw significant commercial development.  King Road before the work on the underpass began.

The North section is now paved with traffic markings, and has had sidewalks and curbs installed. The creek is now flowing through the channel and over the creek bridge.

The overall scope of work to construct the road through the underpass is to add the asphalt and granular road bases and place concrete curb & gutter and sidewalks within the roadway underpass.

FULL road closures will be in place from October 15, for 8 weeks.  King Road will signed as closed, local access for businesses and residents will be maintained. This closure is intended to reduce through traffic.

Access to home and business during normal construction hours (Monday to Friday, 7 a.m. to 5:30 p.m.) may at times be difficult.  Additionally, driveways will be temporarily closed when work is being carried out in the immediate vicinity. Either the inspector or the contractor will notify you of access interruptions prior to the closure.

For day-to-day construction inquiries: Jason Forde at 905-335-7600 ext. 7421

When the work is completed will the city see the development of new business opportunities on the northern part of King Road where there is a considerable amount of prime commercial land on the west side?

Will there be some additions to the commercial business on King Road south of the railway crossing?  The whole purpose of the grade separation was to limit the number of times traffic was halted due to rail traffic.  The GO train increase in their schedule to half hour service would have made it all but impossible to rely on that Road for transportation to the numerous businesses north of the rail crossing.

Aldershot now has a road with no stoppage due to rail traffic.  Will that result in business development?  The city could certainly use the tax revenue that comes from the commercial sector.