Did the GO train screw ups impact you? Here's what happened

 

By Staff

November 2nd, 2021

BURLINGTON, ON

 

Did the GO train schedule screw up impact you this past weekend – Oct. 30 and 31?

Metrolinx explains what happened.

There is never a good time to shutdown the busiest commuter rail line in the country.

This past Saturday (Oct. 30) was particularly rough with the combination of Halloween festivities, sporting events, and concerts all drawing people to downtown Toronto.

So, what happened? During a routine track inspection, GO Transit crews discovered a section of the tracks between Port Credit and Clarkson GO stations was unstable, so much so that trains could no longer pass through the area safely.

The transit agency made the difficult decision to shut down that section of track.

This huge hunk of equipment was brought in to smooth and stabilize the tracks which then had to be tested to ensure the tracks were stable. It could have been worse and happened during rush hours.

Making the fix

Behind the scenes, transit experts at Metrolinx drew up a plan to keep people moving and got started immediately on the repairs. Extra GO buses were called in to shuttle people between Port Credit and Clarkson, and Lakeshore West train service was reduced to hourly to avoid further delays.

The team initially estimated it could take up to 24 hours to complete the repairs but crews worked through the night – during the rain – on Saturday to get the repairs done as quickly as possible, in hopes of reducing the impact to people on Sunday.

Once the initial repairs were made, a large machine known as a DynaCAT was brought in to smooth and stabilize the tracks. Finally, GO had to run a test train over the repaired section at slow speeds to make sure everything was good to go.

In the end, the teams got the job done in time for regular GO train service to resume on Sunday morning.

 