Joseph Brant hospital rebuild is changing the city skyline; scheduled to open in 2018

jbhhealthBy Staff

December 23, 2015

BURLINGTON, ON

 

Each day the re-developed Joseph Brant Hospital takes its final shape.

The last pouring of concrete for the Level 7 slab is almost complete and the vertical from Levels 7 to 8 continues to progress until the New Year.

Pouring for Level 8 has begun and there will be 5 pours in total for this Level. The last pour will be done in early January.

Hospital cranes

A long distance view of the cranes in the sky on the hospital construction site with the Festival of Lights in Spencer Smith Park in the foreground.

The vertical from Level 8 to 9 has started and will continue from now until early January.

The first pour for Level 9 will happen by the end of December. There will be 5 pours in total for this floor and the work will continue throughout January.

The construction of 6 elevator shafts and 3 main stairways from Levels 7 to 8 and 8 to 9 is underway.

Mechanical work, plumbing, electrical and duct work continues on the Main Level, Level 1 and Level 2 throughout the rest of December and the first couple of weeks in January.

Installation of drywall has begun on the Main Level and Level 1

The Building Envelope (also known as curtain wall) has started on the Main Level.

If you would like to be a sidewalk superintendent CLICK HERE and watch a live feed of the construction site.

Demolition of the second section of the loading dock is complete. The construction of micro piles is also complete and excavation for footings will happen at the end of December/Early January.

The new Engineering department is in the final stages of completion with equipment set-up and painting almost complete. The department will be open in early January.

Return to the Front page
Print Friendly, PDF & Email

Comments are closed.