By Staff
November 8th, 2016
BURLINGTON, ON
We now know what the City Solicitor told members of city council when they went into closed session yesterday afternoon.
The Ontario Superior Court of Justice has ordered Burlington Airpark Inc. to pay City of Burlington court costs in the amount of $118,327.53.
The cost award is related to the June 30, 2016 decision of the Ontario Superior Court of Justice in favour of the City of Burlington’s application to compel Burlington Airpark Inc. to submit an application for a site alteration permit to comply with the city’s bylaw.
With the court ruling, the Airpark was required to file an application for a site alteration permit for the fill deposited between 2008 and 2013 before Aug. 31, 2016 and has now been ordered to pay the city’s court costs on a substantial indemnity basis.
An appeal by Burlington Airpark Inc. to the June 30, 2016 judgement in favour of the City of Burlington is scheduled to be heard by the Ontario Court of Appeal on March 28, 2017 at Osgoode Hall, 130 Queen St. West in Toronto.
The City of Burlington site alteration bylaw 64-2014 regulates the placing, dumping, cutting and removal of fill or the alteration of grades or drainage on a piece of land. Individuals doing this type of work must first submit an application to the city for a site alteration permit.
This is getting to be a very expensive experience for the Air Park and almost a profit center for the city. This is not the first time a Court has ordered the Air Park to pay the city very substantial costs.
It’s a Pyrrhic victory; i.e., not cause for celebration.
The $118K is also not much of a deterrent when the “airpark” has collected millions in dumping fees.