Road construction in New Street from Cumberland Ave. to Hampton Heath Rd.

notices100x100By Staff

March 12, 2016

BURLINGTON, ON

New street is what is known as a Regional Road – the region gets to take care of it.

The current task is to replace water mains and wastewater main relining on New Street from Cumberland Ave. to Hampton Heath Rd.

New Street constructionProject is expected to last until September.

The construction work throws a real wrench into the transit schedule.  Here’s the detail:

Burlington Transit users will experience detours and schedule changes from March 21 until September 2016 during construction on New Street.
Detours will affect parts of Routes 4, 10, 50, 52, 300, 301 and 302. Route 4 will not stop on Teen Tour Way from May 9 to Sept. 3, 2016, but the Community Connection Routes will still reach the stop during the construction.

The schedules for Routes 10, 11 and 20 have been changed to allow for connections at the Appleby GO Station. Route 10 will no longer become Route 20 at the Appleby GO Station which means a transfer will be needed when going between Routes 10 and Route 20. The new Route 20 schedule will increase to every 15 minutes.

Detour maps and supplementary schedules to the Ride Guide will be distributed on buses, in the terminal and all updates will be available online at BurlingtonTransit.ca.

Return to the Front page
Print Friendly, PDF & Email

1 comment to Road construction in New Street from Cumberland Ave. to Hampton Heath Rd. – expected to be completed in September.

  • Fred Crockett

    Didn’t they have this dug up all last year? Are they going to do it again? Why not coordinate things?