Outside of the hospital construction is coming along fine - teams are now focusing on how the place will work for patients.

jbhhealthBy Pepper Parr

January 15th, 2016

BURLINGTON, ON

While the construction of the hospital is on schedule –concrete pours for levels 7 and 8 slabs of the tower are now done, and construction of the building envelope and structural steel work has started, the team that is going to run the place when it opens is gearing up to operate a hospital that will be a lot different than the one we have today.
More on the construction side before we get to the Readiness Team.

wer

It will be up and opened before we know it.

The verticals from Level 7 to 8 are complete and the verticals from 8 to 9 are in progress and will be completed by the end of January. Levels 8 and 9 will be dedicated to mechanical and electrical equipment that will run the building.

Hospital cranes

Construction cranes loom over the hospital site 0 pouring of the slabs for the top floor expected to be done by the end of the month.

• There will be five concrete pours in total for Level 9. The final pour will happen by the end of January.
• The vertical from Level 9 to the roof of the hospital will begin at the end of January and will be completed by the beginning of February.
• The construction of 6 elevator shafts and 3 main stairways from Level 8 – 9 is underway and will be finished by mid-January. Construction of 1 stairway and 2 elevator shafts will continue from Level 9 to the roof throughout January/early February.
• Mechanical work, plumbing, electrical and duct work continues on the Main Level, Level 1 and Level 2 throughout January and February.
• Installation of drywall continues on the Main Level, Level 1 and Level 2.
• Masonry work on the Main Level, Level 2 and Level 4 is happening throughout January and early February.
• The construction of the Building Envelope (also known as curtain wall) continues on the Main Level and will begin on Level 1 soon. If you take a look at the site from the parking garage roof you will see some of the curtain wall panels.
• Structural steel work begins in the Ambulance Garage.
• In our existing hospital, the excavation for footings for the second section of our loading dock is complete and the pouring of concrete for the footings is done. Forming and pouring for the foundation wall has begun and will be completed by mid-January.

You can log into the web camera that runs 24×7 and watch the hospital being built – you get to be a sidewalk superintendent without getting cold.

Construction is on schedule – the people who will run the hospital have been organized into an Operational Readiness Team that will focus on ICAT (Information, Communications and Automation Technology).

“We want staff to feel excited, to be comfortable and confident to move into their new space in a seamless transition so they can operate out of that space on move day,” said Kate Traianopoulos, Project Manager, Operational Readiness.

Trish Hamilton JBH

Trish Hamilton Readiness Project coordinator

Trisha Hamilton, Operational Readiness Coordinator and Registered Nurse is working with 11 programs at the hospital including Emergency, ICU, Finance and Decision Support and IT to ensure staff are prepared to move and operate in our new hospital in 2017. Trisha describes her role: “I meet with my assigned programs and essentially we review every little task that needs to be completed so they can hit the ground running. Staff need to feel comfortable going into that space on opening day because we have patients to care for and we have a lot of safety concerns that we need to address so that everything is smooth right from opening day.”

“Once we move into this new building your entire processes change. It’s a big change and that’s why we need to start early, ” she said. For Hamilton the challenge is “getting right into the minutiae of that program, down to the meat and potatoes of what those programs do and the processes they need to accomplish and how they serve our patients is important.”

Return to the Front page
Print Friendly, PDF & Email

Comments are closed.